675 North Road Construction Schedule by Hakar Qadir Gardi is a document available to read on EtoBox.

What is 675 North Road Construction Schedule about?

The document outlines a preliminary construction schedule spanning 904 days from July 2023 to December 2026. It details 29 tasks related to excavation and shoring for a project at 675 North Road. The schedule includes tasks such as site start up, nine lifts of excavation with associated shoring for each lift, and a final completion date of December 25, 2026.