Kalsel Power Plant Boiler Installation Progress by Prastya Deejay is a document available to read on EtoBox.

The document provides a planned time schedule for the installation and commissioning of a 2 x 65MW power plant known as Kalsel 2. It details the planned completion percentages and dates for various parts of the project including boiler installation, turbine installation, initial firing, synchronization testing and handover of the plant which is planned for November 13, 2011 when the plant will reach commercial operation date. It provides status updates on equipment, piping and other system installations nee