Can I read P&G Warehouse Canopy Erection Log on EtoBox?

P&G Warehouse Canopy Erection Log by Maria Menor is a document available to read on EtoBox.

What is P&G Warehouse Canopy Erection Log about?

This document summarizes the daily progress of purlin splicing work for a Procter & Gamble warehouse project over a period of 30 days. It tracks the number of purlin splices completed each day, total splices to date, manpower deployed, and locations of work. On average 9 splices were completed per day, with a peak of 46 splices on one day. Manpower included 1 project engineer, 1 foreman, 5 fitters and 1 groundman each day. Work progressed through various grid lines and sections of the warehouse over the mon