Conveyor Belt Project Part 2 Analysis by Ammar Baidas is a document available to read on EtoBox.

The conveyor belt project is overallocated for design, development, and documentation resources. Leveling within the project timeline removes overallocation for design and documentation but not development. Leveling outside the timeline shifts the completion date to August 23, 2012. To resolve overallocation, two additional development teams and one external team were added. This allows completion by February 1, 2012 over 530 days for $511,200 total cost. Cash flow and cost details are provided.