Weekly Construction Progress Report by Ryan Tanjung is a document available to read on EtoBox.

The weekly report from PT. Era Karya Konstruksi Nusantara provides a progress update on the Sunshine Project construction work for PT. Unilever Oleochemical Indonesia. Based on the report, as of February 11-17, 2022: - 50% of preliminary work was completed including project management, safety facilities, and documentation. - 30% of surveying work was finished including pile set out drawings. - 21% of insurances and other costs were covered. - 36% of soil excavation and top up was finished to prepare f