EOT Proposal for 48.6 Km Project by Dipak Patel is a document available to read on EtoBox.

The document provides details of a road project including: 1) The project length is 48.6 km with a total sanctioned cost of Rs. 509.18 Crore and contract value of Rs. 298.11 Crore awarded to M/s H G Infra Engineering Ltd. 2) The current physical progress of the project is 45.58% with an expenditure of Rs. 99.31 Crore against a scheduled completion date of 26th July 2019. 3) The contractor has requested for an extension of time (EOT) citing delays in land acquisition and permission for utility shifting affe