What is Extension for Mabini Barangay Roads Project about?
The Municipal Bids and Awards Committee of Gamu, Isabela passed Resolution No. 2020-001 to recommend extending the implementation period of a road rehabilitation project by 45 days. This was due to a request from the contractor citing over a month of continuous rain in November and December 2019 as causing a possible delay. The committee resolved to grant the extension following national procurement guidelines regarding infrastructure project contracts. The resolution was then forwarded to the Municipal May