IPC No. 9 for Akaki Bridge Project by hagos aregawi is a document available to read on EtoBox.

- This is an interim payment certificate for the Akaki Bridge Construction Project, covering work done from June 1-30, 2018. - The contractor, IFH Engineering PLC, is being paid 4,776,739.36 ETB for work on various technical specifications including earthworks, structures, and incidental works. - To date, the project has paid the contractor a total of 111,933,295.34 ETB for work that is 64.35% complete, based on the original contract price of 148,450,442 ETB.