What is JAWA1 CCGT Power Plant Inspection Report about?
The document is a request for inspection of steel structure frame members for the JAWA1 CCGT Power Plant project. It requests inspection of the carrying in and unloading of steel frame members on November 17, 2019 at 9:00 AM to check for any damage during transportation or to temporary pieces. It also requests checking the friction joint surfaces on the same day and time. The purpose is to inspect for any issues before use of the materials in construction.