CCPM for Type 36 Housing Efficiency by juma.coin7 is a document available to read on EtoBox.

This study explores the implementation of the Critical Chain Project Management (CCPM) model to enhance time efficiency and reduce costs in a Type 36 housing project. By minimizing safety time and incorporating buffers, the project completion time was reduced from 18 to 15 working days, resulting in a cost saving of Rp.10,907,170.03. The research highlights the effectiveness of CCPM in managing project timelines and improving overall project performance in the construction sector.