ASME BPVC VIII Div 1 Welding Plan by suganth is a document available to read on EtoBox.
This document outlines a welding plan to complete 17,147 joints by March 31, 2019. It details the joint schedules, planned production rates by month, crew assignments, and patches identified for automatic and semi-automatic welding. The main goals are to finish the main line by February 28th and tie-ins by March 8th. Production is planned to ramp up from 377 joints in September to a peak of 3,565 joints in January before dropping to 400 joints in March. Five crews are assigned including two automatic crews