Daily Progress Report: Embankment Works by CharleneMendozaEspiritu is a document available to read on EtoBox.
The daily progress report summarizes the manpower and equipment used for embankment works on March 17, 2020. It lists 23 total workers from 3 companies, including 9 site engineers, 1 safety officer, and 8 operators. 11 pieces of equipment were used, including 1 excavator, 1 mini backhoe, 1 mobile crane, and 2 dump trucks. Today