Slab Floor Concrete Process Schedule by Muhammad Ridhwan Bin Abdul Wahab is a document available to read on EtoBox.

What is Slab Floor Concrete Process Schedule about?

The 14-day rescheduling of a concrete slab floor involved preparing materials like 120 bags of cement and 10 tons of sand, knocking slab positions to level the floor over 2 days, increasing and marking height levels every 10 feet for 2 days, adding mortar to increase floor leveling for 2 days, waiting 1 day for mortar to dry, checking leveling with a water indicator and rope for 1 day, and coating the slab for finishing over 4 days using a 6-8 person work crew.

Author
Muhammad Ridhwan Bin Abdul Wahab