Link Bridge Work Programme Overview by Chezy629 is a document available to read on EtoBox.
The document outlines a 9-week work programme to install a link bridge, including installing hoarding in the first week, removing interfacing MRT components like louvers and handrails in weeks 2-3, installing the last section of the link bridge in week 4, framing and pouring concrete slabs in weeks 5-6, installing the roof, panels, tiles and handrails in weeks 7-8, and removing hoarding in week 9.