Barge Loading Process for PHC Piles by Yudith Bdoel Abdullah is a document available to read on EtoBox.
The document outlines procedures for loading cargo onto a ship or barge. It specifies that the cargo (PHC piles) must be ready 2 hours before berthing, including 1087 pieces weighing 3488.82 tonnes. Loading is estimated to take 3 days using 29 trailers per day carrying 10-12 piles each. The process requires 2 cranes with a minimum 28m boom and 10 cubic meters of wooden dunnage. Cargo is loaded uniformly from bow to stern while maintaining trim and draft, overseen by inspectors. Upon arrival, unlashing and u