RFSU Process for Oil and Gas Projects is a document available to read on EtoBox.
1) Construction disciplines conduct final inspections and testing to establish punch lists. Pre-commissioning activities include pipe blowing, flushing, clearing, lubrication, motor and panel testing. 2) A final joint inspection is conducted and punch lists are reviewed, including new items discovered. Construction and pre-commissioning review is conducted and field trouble reports are issued. 3) Systems undergo commissioning one by one or in groups. Upon completion, system completion certificates are iss