Suntrust Verona Housing Progress Report by Allen Mendoza is a document available to read on EtoBox.

This report provides progress details for the construction of a housing unit in the SunTrust Verona project. It outlines the various construction items and their budgeted costs, as well as the percentage of work completed to date for each item. To date, 100% of the excavation, formworks, and reinforced concreting works have been completed. 95% of the CHB walls and formworks & scaffolding are finished. However, no work has begun on plastering, tiling, carpentry works, doors and windows. The total contract am