Daily Construction Progress Report by Alpesh HiRani is a document available to read on EtoBox.

The daily report for the Kenyatta Stadium project on January 21, 2025, indicates that construction activities are progressing well, with various tasks completed including excavation, foundation walling, and casting of slabs across multiple pavilions. The report notes a total workforce of 74, with challenges faced due to the absence of electrical subcontractors on site. Weather conditions were sunny, and no time was lost due to rain.