Opening book details…
Can I read Uno Bridge Pipe Bridge Schedule on EtoBox?
Uno Bridge Pipe Bridge Schedule by sdsantiago.terwdcares is a document available to read on EtoBox.
What is Uno Bridge Pipe Bridge Schedule about?
The document outlines the time schedule for the Pipe Bridge Crossing project at Uno Bridge in Teresa, Rizal, with a duration of 30 working days starting from October 15, 2023. It includes a detailed list of tasks such as pavement cutting, excavation, pipe laying, and restoration works. The document is prepared by Lou Gredson H. Mored, checked by Engr. Gilbert Roland R. Denilla, and approved by Ms. Marnelle D. Maala-Reyes.
- Author
- sdsantiago.terwdcares
- Language
- EN