Can I read Wing Wall Construction Schedule on EtoBox?
Wing Wall Construction Schedule by Jojo Dejucos is a document available to read on EtoBox.
What is Wing Wall Construction Schedule about?
The construction schedule outlines 4 key activities for the North Marine Road project starting on August 18th and running through September 23rd. Activity 1 involves duct bank construction over 36 days and requires an excavator, foreman, carpenter, and laborers. Activities 2 through 4 involve pipeline crossing, culvert wing wall construction on the left and right sides, each taking 15 days to complete and involving excavation, concrete pouring, and backfilling.