EQ 2 to 5 Project Financial Progress by RAMKUMAR is a document available to read on EtoBox.
This document provides a progress update as of July 31, 2016 for the EQ 2 to 5 project. It summarizes the financial and physical progress as follows: 1) Financially, 14.23% of the total budget has been spent, with 3.83% spent on substructure works and 0.14% on dismantling works. 2) Physically, 48 of the planned 63 guide walls have been completed, with 6 of the planned 18 tidal defense walls constructed. 3) For tidal defense and adjacent walls, the actual construction in July was 6 and 8 walls respectiv