Newtown Creek Project Schedule 2013 by wholmes5924 is a document available to read on EtoBox.
What is Newtown Creek Project Schedule 2013 about?
This document provides a Gantt chart schedule for the Newtown Creek Remedial Investigation/Feasibility Study from 2012 through 2018. The schedule outlines 27 total tasks, including field work, data interpretation, risk assessments, modeling, and reporting. Key milestones include submitting the Phase 2 Work Plan by April 2014, the Draft Baseline Ecological Risk Assessment Report by May 2015, and completing the Feasibility Study Report by November 2018. Monthly update meetings with USEPA are planned throughou