Daily Structural Progress Report - Dahej by j is a document available to read on EtoBox.

What is Daily Structural Progress Report - Dahej about?

The Daily Progress Report for the Detergent Project at Dahej Plant on February 2, 2025, indicates ongoing structural work with a cumulative progress of 968.468 MT, representing 4.43% completion. Key activities include marking, cutting, and welding, with several tasks still pending due to the lack of GA drawings from Shroff. The report highlights the need for the release of drawings to proceed with various construction activities.