Clean Steam System Qualification Guide by Doan Chi Thien is a document available to read on EtoBox.
The document provides guidance on sampling plans for commissioning and qualifying clean/pure steam systems. It recommends a risk-based approach and defines three phases of qualification: Phase 1 demonstrates production and delivery over 3 days; Phase 2 demonstrates stable production over 1 week; Phase 3 continues testing for 4 weeks with modified sampling. Additional steam quality tests are needed if steam will be used for sterilizing porous loads for European markets.