What is PEECC Cable Trench Progress Report about?

The document provides a status update of various civil works for a power plant project. It lists 7 cable trench works and their current progress, ranging from 0% to 47% completed. Other works mentioned include the electrical control building, transformer foundation, boundary wall (120/846m completed), gantry foundation, GIS foundation, and PEECC foundation (90% completed). Civil has committed revised completion dates between 15 January to 3 February 2017 for most unfinished works, pending receipt of require

Author
Rachit Khanna