What is Olkiluoto 3 Simplified Case Study about?
The Olkiluoto 3 nuclear reactor project in Finland aimed to increase electricity supply and reduce energy imports but faced significant delays, taking approximately 18 years instead of the planned 4 years. The project experienced major cost overruns, with expenses rising from an estimated €3 billion to between €9–11 billion due to supply chain issues, weak oversight, contractor disputes, and poor planning. Key lessons include the importance of realistic planning, completing designs before construction, ensu