Can I read Icon Plaza Phase 1 Exhaust Data on EtoBox?

Icon Plaza Phase 1 Exhaust Data by romelsb is a document available to read on EtoBox.

What is Icon Plaza Phase 1 Exhaust Data about?

The document provides production projections for rebar, formwork, and concreting activities for Phase 1 of the Icon Plaza project. It shows that rebar installation was 55% complete in October 2010 but fell behind schedule in subsequent months, reaching only 88% by mid-February 2011. Formwork installation followed a similar trend, reaching 54% complete by mid-February against a target of 46%. Concrete pouring was 19% complete in October 2010 and reached 74% by mid-February, lagging the target of 26%.