The Khamane-Oxbow Road Project in Lesotho aimed to upgrade a 22 km gravel road to bitumen standard for improved transportation. While the road was substantially completed in 1990, 17 months behind schedule, major issues included contractor delays, weather impacts, and a modified pavement design. The total cost of $8.66 million exceeded appraisal estimates by 20%. Traffic levels were also much lower than predicted, reducing the economic rate of return from 16.97% to 6.20%. Key lessons included ensuring suita