Project Timeline for Excavation Tasks by Almutahir is a document available to read on EtoBox.
This document contains a Gantt chart showing the schedule for clearing, excavation, sloping, filling, and compaction tasks over a 31 day period from August 23rd to September 22nd 2018. The tasks include clearing for 2 days, excavation for 27 days, sloping for 2 days, filling for 4 days, and compaction and spreading for 5 days, with some tasks dependent on the completion of prior tasks.