1. The company plans to manufacture a product consisting of 3 parts (A, B, C). It will take 5 weeks to design the parts and determine assembly. It will then take 4, 5, and 3 weeks to make parts A, B, and C, respectively. Part A must be tested for 2 weeks after completion. Assembly will take 2 weeks for parts A and B, then 1 week to attach part C. The final product requires 1 week of testing. 2. The project network diagram shows 10 activities with durations and predecessors. The critical path and total flo