Rail Vikas Nigam Limited has completed the Janghai-Phaphamau Doubling project, with Phase II commissioned on January 4, 2025. They are ready to start the Non-Interlocking process for the remaining work at Phulpur Yard from March 8, 2025, aiming for commissioning on March 13, 2025. A day-to-day program has been submitted to the LKO Division for further action.