Philippine Construction Productivity Rates by Nick Operario is a document available to read on EtoBox.
What is Philippine Construction Productivity Rates about?
The document provides productivity ratios for various construction activities measured in manhours per unit. It lists ratios for excavation, backfilling, trenching, concrete works, formworks, carpentry, structural steel works, masonry works and more. Excavation by hand takes 6 manhours per cubic meter compared to 0.5 manhours by machine. Concrete works require 2.54 manhours per square meter for formworks and 8.54 manhours per cubic meter for concreting. Structural steel fabrication takes 110-130 manhours pe