Can I read 220kV Substation Precommissioning Report on EtoBox?
220kV Substation Precommissioning Report by palamaner220kv is a document available to read on EtoBox.
What is 220kV Substation Precommissioning Report about?
The pre-commissioning test report for the 220KV Sub Station Madanapalli, conducted on March 21, 2024, details various electrical tests including short circuit, open circuit, magnetic balance, ratio, insulation resistance, and DC resistance tests. The transformer has a capacity of 100 MVA with a vector group of YNa0d1 and was manufactured by EMCO in 2005-2006. All tests were performed successfully, confirming the operational integrity of the transformer.