D06H Premset Project Handover Certificate by websterchikamba is a document available to read on EtoBox.
The document is a Handover & Acceptance Certificate for the D06H 11kV Premset Extension Projects, completed on 12 June 2025 for Delta Kwekwe Maltings. It outlines the scope of works including supply, installation, and commissioning of electrical equipment, along with testing results. The project has been certified as completed and handed over to the client, with remarks on future transformer energization.