Konawe Nickel Pipe Bridge Cost Estimate by ardiansyah.ardiansyah is a document available to read on EtoBox.
The document outlines the construction work order for the Pipe Bridge Cahaya 2 as part of the Konawe Nickel Development Project, detailing cost estimates and project management information. It includes specific quantities and costs for engineering, earthwork, civil work, and management, totaling $769,202.92. The document is marked as restricted information and contains proprietary data for the construction project.