SUSTIO Project Schedule R1 by Teh Jenn Hooi is a document available to read on EtoBox.

What is SUSTIO Project Schedule R1 about?

The SUSTIO Project outlines the schedule for hydrant pipe rectification, detailing six key activities over a span of six days from January 24 to January 30, 2023. Each task, including leakage scanning, slab marking, hacking, pipe rectification, pressure testing, and final inspection, is allocated one day. Notably, the leakage scan is scheduled to start at 9 PM for optimal accuracy.