Skip to content

Opening book details…

About this document

Construction Project Timeline Analysis by Kilk Sue is a document available to read on EtoBox.

The document outlines the schedule and critical path for activities in a construction project. It lists 22 activities from A to U with their duration in days. It then calculates the earliest and latest start and finish dates for each activity, determining that the critical path takes 78 days and includes activities A, B, D, E, F, G, H, I, J, K, L, M, P, R and T.

Author
Kilk Sue
Language
EN