Can I read Lakbi Fishery Harbour Project Report on EtoBox?
Lakbi Fishery Harbour Project Report by Humaid Niyazi Had's is a document available to read on EtoBox.
What is Lakbi Fishery Harbour Project Report about?
The daily report for the Lakbi Fishery Harbour project indicates that mobilization started on June 6, 2024, with a total duration of 682 days and a completion date set for April 18, 2026. As of December 29, 2024, various activities are ongoing, including design and engineering studies, soil investigations, and environmental assessments. Current manpower consists of 8 personnel, with a mix of Omani and non-Omani workers, and equipment status shows all owned vehicles are operational.
- Author
- Humaid Niyazi Had's
- Language
- EN