Can I read Mangla Project June 2023 Progress Report on EtoBox?

Mangla Project June 2023 Progress Report by Ali Hanif is a document available to read on EtoBox.

What is Mangla Project June 2023 Progress Report about?

The Mangla Refurbishment Project site progress report for June 2023 provides updates on work for various packages. For Package 1+7, stator installation is underway for Unit 3 and insulation work is progressing for Unit 4. Defect liability periods have started for Units 5 and 6. Package 5 is working on penstock and intake gate refurbishment. Package 6+8 is installing main transformers for Units 3 and 4. Package 9 recently completed a planned shutdown and is addressing trouble reports.