أهمية تقليص مدة انجاز المشاريع في تخفيض التكاليف غير المباشرة - دراسة حالة مشروع 20مسكن بالاغواط by mdsakibmolla879 is a document available to read on EtoBox.

This study emphasizes the significance of project crashing techniques in reducing indirect costs and accelerating project delivery in construction. A case study on the construction of housing units in Laghouat State demonstrated that applying crashing reduced project completion time from 100 weeks to 78 weeks and decreased indirect costs from 10,000,000 DZD to 7,800,000 DZD. The findings suggest that project duration reduction techniques offer new solutions for project management challenges.