Vemagiri 400/220 KV Substation Overview by MMK29 is a document available to read on EtoBox.
The 400/220KV Vemagiri substation in East Godavari District, Andhra Pradesh was commissioned on September 10, 2005 by energizing the bus from the 400KV Kalapaka-Vemagiri transmission line. The substation was initially energized with 24 bays including 14 400KV feeders and 4 220KV feeders. It is located 10KM from RJY Railway station near National Highway 5 opposite the Andhra Bhoomi press in Vemagiri village. The construction of the substation was undertaken as part of the SIMHADRI-VIZAG power transmission sy