Earned Value Analysis for Project Management by Nobukho Njenje is a document available to read on EtoBox.

The document discusses earned value analysis metrics for two project examples. For the first project, the metrics calculated at the end of the second day include BCWS of R250, BCWP of R170, ACWP of R200, SV of -R80 and CPI of 0.85. For the second project, metrics calculated at week 3 include BCWS of R7,500, BCWP of R5,000, ACWP of R9,000, CV of -R4,000 and SV of -R2,500. The project is behind schedule and over budget, so the manager may reduce scope, extend schedule, obtain more funding or use overtime.