Revised Embankment Quantity Calculation by Rolly Marc G. Sotelo is a document available to read on EtoBox.
This document provides revised quantity calculations for embankment and roadway excavation for a proposed detour road project between station 0+000.00 to 0+678.99. It calculates that 6,796.88 cubic meters of embankment will be needed from borrow and 230.78 cubic meters will come from 80% of the roadway excavation volume of 287.23 cubic meters. Tables show station-by-station area and volume calculations for the embankment and roadway excavation quantities.