Time Optimization in Gresik Project by Ajie Dhohan is a document available to read on EtoBox.

The document discusses time optimization methods for a construction project in Gresik District, Indonesia. It analyzes the project using CPM, PERT, and PDM methods. CPM analysis showed a completion time of 57 weeks. PERT analysis estimated 78 weeks with 99.87% probability of on-time completion. PDM analysis produced the shortest time of 30 weeks, making it the best fitting method for the project.