Can I read Alwitra MAG 6 Weekly Progress Report on EtoBox?

Alwitra MAG 6 Weekly Progress Report by Dalia Fathy is a document available to read on EtoBox.

What is Alwitra MAG 6 Weekly Progress Report about?

This weekly progress report summarizes the project status from April 18-23. Shop drawings of basement floor columns were submitted this week and approved. Four column shop drawings detailing dimensions from foundation to lower ground levels were submitted and approved on April 13-14. The look ahead plan includes submitting 12 core wall dimension drawings, 8 core wall reinforcement drawings, 6 lower ground floor column and axis drawings, and 4 lower ground floor slab dimension drawings between April 22-24.