Can I read Installation Test Report for 250KVA Sub-Station on EtoBox?
Installation Test Report for 250KVA Sub-Station by Khairul Hasan is a document available to read on EtoBox.
What is Installation Test Report for 250KVA Sub-Station about?
The installation test report for a 250KVA sub-station at Tahurun Nessa, Dhaka, includes results from various tests such as transformer continuity, insulation tests for transformer, LT and HT panels, LT and HT cables, and earthing resistance. All insulation tests show high resistance values, indicating good insulation integrity, and earthing resistance values are within acceptable limits. The report was prepared by Mahtab Uddin, a licensed supervisor from Mech Power Engineering.