Here is a potential crashing schedule that meets the project deadline in the minimum number of days at the lowest possible cost: - Activity a: Crash to 8 days at a cost of $400 * 2 days = $800 - Activity b: No change needed - Activity c: No change needed - Activity d: Crash to 3 days at a cost of $400 * 2 days = $800 - Activity e: No change needed - Activity f: Crash to 1 day at a cost of $800 Total project duration = 8 + 6 + 4 + 3 + 9 + 1 = 31 days Total crashing costs = $800 + $800 = $1600 The proje