Schedule of PLTM Sei Wampu Tasks by Josua Ferry Manurung is a document available to read on EtoBox.

The schedule outlines the work for the Sei Wampu Hydropower Plant project from May 2016 to June 2017. Key milestones include: 1) Construction of coffer dams from May to July 2016 to allow work in the river area. 2) Construction of the dam up to elevation 136 from July 2016 to November 2016. 3) Construction of the powerhouse from June 2016 to October 2016 including the intake structure, penstock, and turbine installation. 4) Ongoing powerhouse construction from August 2016 to June 2017 including conc

Author
Josua Ferry Manurung
Language
EN