Can I read Flow Line Weekly Update Report on EtoBox?
Flow Line Weekly Update Report by Omer ali is a document available to read on EtoBox.
What is Flow Line Weekly Update Report about?
This weekly update provides the status of activities for the UTMN-2294 flow line project. Key details include: - Right of way and flow line excavation are nearly complete at 6000 LM and 6130 LM respectively. - Welding and coating of joints is ongoing, with 471 joints welded and 399 joints coated so far. - Several crossings are over 60% completed, including marl road, above ground pipeline, and underground cable crossings. - Pipe lowering and backfilling activities have made good progress at 5900 LM and 575
- Author
- Omer ali
- Language
- EN